Friday, November 28, 2014

Right elevator complete, wing main ribs straightened

Friday we guys snuck out to the garage after the ladies returned from propping up the local economy.
First we finished deburring & riveting the rolled leading edge of the right elevator.
Dad worked at the grinder on a couple 6" scraps of flat bar steel & 3/8" bar steel that I acquired for use as bucking bars. They need a little polishing, but we've already tried out one and it'll be a nice addition to the toolbox.
Meanwhile our lovely assistants helped strip the vinyl off of the right elevator and inspected our work.
 

Another finished part!! I also brought in the rib flange straightener and Dad worked on the wing main ribs while the rest of us were yakking after dinner.
 
Empennage: 2 hrs
 
Wings: 1 hr

Thursday, November 27, 2014

Right elevator assembly, elevator trim tab progress

We flew in a bunch of help for the Thanksgiving weekend; first Natalie had to train the new recruits.
 After Uncle Benny passed her inspection (clecoing, drilling deburring, riveting on practice material), he set to work riveting the right elevator counterbalance skeleton together. He really leaned into it.
The flange-nosed yoke I bought was essential here, as I only had 1 flat die that was long enough.
 Next he & Dad riveted on the spar reinforcement plates and nutplates for the control bushings.
 With those on we installed the root rib with flush head rivets; these were a bit tricky to get to but all 4 rivets turned out pretty well.

Our lead helper came back to check on us & attach the right elevator horn.
Skeleton complete!
Per the suggestion of the Van's instructions we installed these two rivets to avoid having to install blind rivets later.
 That done, the skeleton slid in easily, the counterweight fit nicely and we proceeded to rivet the skin to the skeleton. 
 After finishing the bottom skin I remembered that we hadn't applied the black RTV at the intersection of the stiffeners inside the skin; access was tight, so we made a bit of a mess, but we got it in just the same.
 While the guys set some of the skin rivets and prepared to roll the leading edge I worked on bending the left elevator trim tab tabs.
 These were easier to bend than the tabs on the elevator itself, mostly because I used more double-sided tape and was able to clamp them more securely.
 We headed in to carve the turkey with a nearly complete elevator! We got the leading edge rolled, match-drilled and ready for deburring. Man, these things go together fast with lots of help.
 Dad picked up right where he'd left off after helping start the horizontal stabilizer last fall, and Ben picked it up quick. It's just a shame we're a thousand miles apart!
 
Empennage: 5 hrs

Monday, November 10, 2014

Left elevator tab bending, wing tank skin platenut drilling & deburring

I decided to tackle bending the tabs on the left elevator skin and trim tab. Rumor has it this is and the trim tab are the most common areas for mistakes on the empennage.
I stripped the vinyl from the tab area and marked a line perpendicular to the trim tab cutout. Then I fabricated some bending blocks at an 11 degree angle based on a survey of other builders' sites and a check with my protractor of the elevator finished angle.
The blocks were taped into place with double-sided tape. The pictures in the manual describe clamping it to the table, but they only show this for the trim tab, and I couldn't find an effective way to clamp the blocks while leaving myself enough room to work. Instead I clamped the elevator and the rear spar on both ends and hand-clamped the blocks while I worked first the bottom tab, then the top.
My lines must have been slightly too far inboard of the ideal, because I had to file the edge of the bottom tab to get it to clear the upper tab (in the photos, the bottom side is up).
Other than the filing, with some patience, a block of wood, and finishing the tab with the rivet gun & mushroom head set at 10 psi, the bottom tab moved into place.
 
The upper tab seemed to go smoothly as well until I hit it with the rivet gun. The block must have moved out of place, causing the radius of the bed to go from 1/8" (per spec) to about 1/64" (too small).
This could be a problem as radii less than 1/8" can lead to cracking at the bend.

I'll send the photo in to Vans and see if I need to remove the tab and fabricate a replacement, or if it's acceptable and just bears close inspection to ensure cracks don't form.

Aside from that minor setback, the tab bending was easier than I expected. I set the elevator aside and with help from Brian Judge pulled out the wing spars to mark orientation.
We noticed a spot near the etched serial numbers that looked like corrosion; it appears that the riveter may have skipped off the surface. I removed the corrosion with scotchbrite, and will clean & prime this later.
We drilled out the #40 holes for the tank skin platenuts, Brian deburred on the inside of the spars while I worked with the countersink on the outsides.
And then with the help of this lovely assistant we squeezed the first rivets on the wings!
Brian got to try his hand using the squeezer - his first rivets on the plane.
While I continued chewing aluminum with the countersink, Brian started edge-deburring the right rear spar.
We made great progress, and are officially started on the wings!! And almost exactly one year to the day that we started the empennage it's essentially finished - right on schedule. Not bad for a spring and summer where it felt like we were never home.
 
Thanks again to all the family & friends who've helped so far, and for those who haven't - you will.
 
Empennage: 2 hrs
 
Wings: 3 hrs

Saturday, November 8, 2014

Elevator deburring, dimpling, priming

With the girls out at a tea party I finished deburring and dimpling all elevator parts (sans trim tab) and scuffed, cleaned and primed them.
I scuffed the counterbalance skins but caught my mistake before I primed the outside. Good thing I'm painting this plane!
Next up I edge-deburred both skins and dimpled them. There were a couple of hard-to-reach holes that I need to build a reach stick & hit with the dimple die in the rivet gun.
I also drilled the last holes in the skins where the fiberglass tips will attach to #30 and deburred and dimpled them, as I'm pretty sure it would be impossible to get in there after the elevators are riveted up.
Two piles of parts, ready to go!
I'm going to hold off on riveting the right rudder so I can close it up over Thanksgiving with family that will be in town. I may continue with the left including trim tab & trim assembly in the meantime.
 
Empennage: 7 hrs

Sunday, October 26, 2014

Elevator match drilling, disassembly, deburring

With the rudder buttoned up, we switched back to match-drilling the elevators.
I fitted the elevator control horns to the respective spars and match drilled the holes to #30.
Next up was match-drilling the skins to the understructure. These 1" and 1/2" jaw cleco clamps made matching up and drilling the non-factory punched holes a breeze.

I had some help disassembling the right elevator...

But the left was on me.
We finished the day with 2 piles of parts ready for deburring, edge finishing and dimpling!
Brian Judge came over for a couple of hours Saturday to help me puzzle through fabricating the support brackets for the wing stand. No pictures, but we carved up a lot of aluminum angle preparing for it.
Sunday we were back at it with Erin deburring & stripping rivet lines while I machine countersunk holes in the main spars, end ribs and E-606 top flange.
Many builders modify a microstop countersink cage to access holes close to the rib flanges, but I found that careful use of a manual hole deburring tool with a countersink bit gave me a clean result - in come cases better than my drill press with the cage installed!
Another good couple of sessions, more parts ready for priming, and a daughter who said she had a fun weekend and wished we had another day. Can't ask for more than that.
 
 
Empennage: 7 hrs

Saturday, October 18, 2014

Rudder complete!

I put off back-riveting the trailing edge as long as I could, and finally ran out of excuses. I decided to follow several other builders' paths and alternate shop head/manufactured head to try to limit any distortion (Van's limits deviation from a line stretched from top to bottom of the rudder along the trailing edge to 0.10").
 First I taped in half of the rivets, then followed Van's instructions, partially setting every 10th rivet, then every 6th.
 The 3x rivet gun with a back-rivet set at about 40 PSI made this easy, and I was glad to have practiced this in the EAA Sportair Workshop.
 The rivet set starts vertical relative to the rivet, and after a few taps swings perpendicular to the surface of the skin.
 After partially setting all rivets on one side, I flipped the rudder over, finish-set the rivets with the mushroom head rivet set on a swivel at 50 PSI. Once this was done, I repeated the above steps on the opposite side.
I did manage to slightly mar the skin in 2 spots, but all rivets were set clean with good shop heads, and our deviation measured at 0.0470", so we're within tolerance. Whew!
 The last step (for forming metal, anyway) involves rolling the leading edge. Some people buy new dowels for this...
 It took some finesse & re-rolling, but all 3 sections came together.
 I squeezed some pop rivets, and voila - another finished part!!
I still need to install rod-end bearings (which allow the rudder to connect to the vertical stabilizer), and install the fiberglass top and bottom, but I'm calling this one complete.
 
 
Empennage: 2 hrs

Sunday, October 12, 2014

Right elevator stiffeners backriveted

I snuck out to the garage for an hour to back-rivet the stiffeners onto the right elevator and bend the skin. No pics, but we're back on track!

Empennage: 1 hr